Bolero Weekly Progress - 28 June 08

Tim pretty much finish up the structural modifications to Bolero this week. This included closing in the cabin with the installation of the coach roof. In addition he permanently installed the new toe rails. Hid did a stunning job scalloping out the underside of the port toe rail to hide a deck bulge that was a result of a previous chain plate repair.

Project Stats
Total Hours - 577.50
Total Photos - 1571

Click the highlighted days for details.

Sunday Monday Tuesday Wednesday Thursday Friday Saturday

Tim's Total Time This Week 30.75 hrs